ISS On-Orbit Status Report

    ISS Daily Summary Report – 05/07/15

    Bone Densitometer (BD) Imaging On-orbit Replacement Unit (ORU) Remove and Replace (R&R): Following a failed checkout of the BD, ground controllers determined that the Imaging Unit had failed. Cristoforetti R&R’ed the unit today in advance of Rodent Research sample collections next Monday. Ground controllers successfully calibrated the unit and are ready to proceed with Rodent Research …

    Read Full Post

    ISS Daily Summary Report – 05/06/15

    Gene, Immune and Cellular Responses to Single and Combined Space Flight Conditions – A (Triplelux-A): Cristoforetti installed the three Triplelux Reservoir A into the Automatic Ambient Stowage (AAS) inserts. She retrieved the second Culture Tube A from Minus Eighty Degree Celsius Laboratory Freezer for ISS (MELFI), thawed it in the Biolab glovebox and installed it in …

    Read Full Post

    ISS Daily Summary Report – 05/05/15

    Gene, Immune and Cellular Responses to Single and Combined Space Flight Conditions – A (Triplelux-A): Cristoforetti continued operations for run two of two of Triplelux-A. She installed the Experiment Container (EC) in the Biolab Left Rotor (Rotor L) and activated the run. Triplelux-A uses a rat macrophage cell line to investigate and compare the ability …

    Read Full Post

    ISS Daily Summary Report – 05/04/15

    Robotics Refueling Mission (RRM) Operations: Over the weekend, the Special Purpose Dexterous Manipulator (SPDM) picked up Task Board 2 (TB2) and the Safety Cap Tool (SCT) from the RRM. The Mobile Transport (MT) was translated to Work Site (WS) 7 where the SPDM stowed TB2 and the Safety Cap Tool on the RRM On-orbit Transfer Cage …

    Read Full Post

    ISS Daily Summary Report – 05/01/15

    USOS Crew Half Duty Day: Today was a half duty day for the USOS crew. This was payback for the weekend Dragon arrived and the crew performed vehicle arrival activities including critical cargo transfer. NeuroMapping:  Following a control pad connection to the HRF laptop, Virts launched the NeuroMapping application and completed all the tests. The …

    Read Full Post

    ISS Daily Summary Report – 04/30/15

    Robotic Refueling Mission-2 (RRM-2): Virts worked with ground teams to configure the Japanese Experiment Module Airlock (JEMAL) and extend the JEMAL slide table to position the RRM for transfer. The Space Station Remote Manipulator System (SSRMS) operators on the ground are currently using the Special Purpose Dexterous Manipulator (SPDM) to remove task board (TB)3 from …

    Read Full Post

    ISS Daily Summary Report – 04/29/15

    59 Progress (59P) Status:  Last night Russian ground controllers resumed 59P troubleshooting during Russian ground passes and were able to establish communications with the vehicle and review telemetry.  Russian controllers configured the refueling system to feed the thrusters and made two unsuccessful attempts to command the thrusters to stabilize the vehicle’s angular rotation. Per Mission …

    Read Full Post

    ISS Daily Summary Report – 04/28/15

    59 Progress (59P) Status: 59P launched from Baikonur Cosmodrome in Kazakhstan at 2:09 AM CDT and achieved orbital insertion. Shortly after the third stage separation, the ground experienced partial loss of communication with the vehicle. Mission Control Center (MCC)-Moscow attempts to re-gain communication with the vehicle over subsequent ground passes were unsuccessful. The next troubleshooting …

    Read Full Post

    ISS Daily Summary Report – 04/27/15

    59 Progress (59P) Launch/Dock: 59P is scheduled to launch tomorrow from Baikonur Cosmodrome in Kazakhstan at 2:09 AM CDT. Docking to the ISS Docking Compartment (DC)-1 is scheduled to occur tomorrow at 8:07 AM CDT. Rodent Research-2 Center for the Advancement of Science in Space (RR-2 CASIS): Virts and Kelly configured the Bone Densitometer and …

    Read Full Post

    ISS Daily Summary Report – 04/23/15

    Pre-Determined Debris Avoidance Maneuver (PDAM): Last night at 8:00 PM CDT the Flight Control Team was notified of a high concern, late notice conjunction. A PDAM was performed today at 12:35 AM CDT using 58P thrusters. Burn duration was 2 minutes, 20 seconds with a Delta-V of 0.3 meters/second.  Ocular Health: Padalka and Kornienko, with …

    Read Full Post