    CAPSTONE Team Makes Progress Toward Recovery Operation

    Artemis Logo - red rocket trail, blue arch that represents earth, ARTEMIS text, gray half sphere on a white background

    Over the past week, the CAPSTONE spacecraft was able to improve thermal conditions for the propellant and other critical systems while maintaining positive power generation. The operations team has been performing ground and spacecraft testing in preparation for an attempt to stop CAPSTONE’s spin. This operation would return the spacecraft to normal status and will …

    Read Full Post

    Pre-Pressurization Test Complete

    Artemis Logo - red rocket trail, blue arch that represents earth, ARTEMIS text, gray half sphere on a white background

    Launch controllers have completed the pre-pressurization test, obtaining pressure and temperature level readings as desired.  Controllers are continuing with the procedures for today’s test, gathering additional data.

    Read Full Post

    ICPS Liquid Hydrogen in Replenish, Teams Moving Ahead with Pre-Press Test

    Artemis Logo - red rocket trail, blue arch that represents earth, ARTEMIS text, gray half sphere on a white background

    Launch controllers have reached the replenish phase of liquid hydrogen loading operations for the interim cryogenic propulsion stage of the Space Launch System rocket and are continuing operations to load liquid oxygen into the upper stage. Teams are moving into operations to conduct a pre-pressurization test, in which engineers will bring the core stage liquid …

    Read Full Post

    Liquid Hydrogen in Replenish, Teams Move Ahead with ICPS Loading

    Artemis Logo - red rocket trail, blue arch that represents earth, ARTEMIS text, gray half sphere on a white background

    The Space Launch System’s core stage liquid hydrogen tank is now full and is being replenished as some of the supercold propellant boils off. Since resuming liquid hydrogen fast fill operations, the rate of the hydrogen leak at the tail service mast umbilical quick disconnect has remained within allowable rates. The core stage liquid oxygen …

    Read Full Post

    Liquid Hydrogen Filling Operations Resume

    Artemis Logo - red rocket trail, blue arch that represents earth, ARTEMIS text, gray half sphere on a white background

    Teams have resumed the flow of liquid hydrogen into the core stage after warming up the quick disconnect, or interface where the fuel feed line connects to the rocket, to reseat the connection as part of their troubleshooting plan to fast fill the propellant.

    Read Full Post

    Hydrogen Leak Detected During Slow Fill Operations

    Artemis Logo - red rocket trail, blue arch that represents earth, ARTEMIS text, gray half sphere on a white background

    Launch controllers have detected a hydrogen leak in a cavity in the tail service mast umbilical and have stopped flowing the propellant to the rocket while they troubleshoot the issue. Engineers will warm up the quick disconnect, or interface where the fuel feed line connects to the rocket, to attempt to reseat it.

    Read Full Post

    Core Stage Liquid Oxygen Chilldown Complete, Slow Fill Underway

    Artemis Logo - red rocket trail, blue arch that represents earth, ARTEMIS text, gray half sphere on a white background

    After chilling the lines for liquid oxygen (LOX), teams have begun the slow fill phase to load LOX into the Space Launch System (SLS) rocket’s core stage and have started chilling down the transfer line for the liquid hydrogen (LH2). Once LOX slow fill is complete, teams will transition to fast fill operations. Once the …

    Read Full Post

    Launch Director Gives “Go” to Begin Cryogenic Operations, NASA TV Coverage Underway

    Artemis Logo - red rocket trail, blue arch that represents earth, ARTEMIS text, gray half sphere on a white background

    Artemis Launch Director Charlie Blackwell-Thompson has given the “go” to officially begin loading propellants into the Space Launch System rocket as part of today’s Artemis I cryogenic demonstration test. Weather remains favorable for the test. Tanking operations will begin with chilldown of the core stage liquid oxygen transfer line. NASA TV coverage is underway.  

    Read Full Post