Suggested Searches

2 min read

NASA Awards Launch Complex 39B Refurbishment Contract for Kennedy

NASA has awarded a contract to Precision Mechanical Inc. of Cocoa, Florida, to refurbish the Environmental Control System at Launch Complex 39B at Kennedy Space Center in Florida.

The firm-fixed price contract with two options was awarded June 30 and has a maximum value of $11.23 million with a performance period of 412 days.

Precision Mechanical Inc. shall furnish all labor, equipment, materials and related activities necessary for the refurbishment/replacement of the Environmental Control System (ECS) at KSC Building J7-337, better known as Launch Complex (LC) 39B.  The completed ECS will provide conditioned clean purge air to various compartments of the new Space Launch System (SLS) vehicle.  The refurbishment/replacement includes the following components: chillers, large volume blowers, high-pressure ducts, piping, industrial process PLC-based controls, humidifiers and boilers, and associated electrical equipment.  All cooling tower equipment including fill, fans, gear boxes, pumps, valves, piping, grating and handrails will be replaced and the concrete structure repaired/refurbished.

The project also will include two options for the installation of four additional compartment purge circuits and appurtenances from the main distribution plenum to above the pad surface and the replacement of existing post-cooling coils for three cooling chambers.

For information about NASA and agency programs, visit:

https://www.nasa.gov

-end-

Gregory B. Harland
Kennedy Space Center, Fla.
321-867-2468
gregory.b.harland@nasa.gov