NASA EVM Regulations and Requirements
*Integrated Program Management Data Analysis Report (IPMDAR) is effective June 1, 2023, on all new contracts and In-house Projects. Please contact your center EVM Focal Points, CO/CORs, and/or Jon Fleming, Kristen Kehrer with any questions.
- OMB Circular A-11, Appendix J (latest version), requires EVM on all capital asset acquisitions.
- The Capital Programming Guide, is a Supplement to the A-11 Circular and includes EVM requirements in the following sections:
- I.5.5, II.2.4, II.4, II.5, II.8, and Appendix 3
- NPR 7120.5 (latest version) – NASA Space Flight Program and Project Management Requirements Defines when EVM is required and requires projects with EVM requirements to use an EVM system that complies with the 32 guidelines found in EIA-748 Earned Value Management System Standard.
- FAR Overhaul – FAR Part Deviation Guidance
- NASA PCD 25-05A, Class Deviation From NASA FAR Supplement (NFS) Part 1834 To Implement The Revolutionary FAR Overhaul (RFO) (NASA Case 2025-N006)
- NASA FAR Supplement 1834 Companion Guide
- NASA PCD 10-17, Class Deviation to NFS 1816.405-274: Award Fee Evaluation Factors Are Not Directly Tied to Earned Value Management Metrics
- NASA EVM Contract Requirements Checklist
- NASA/Defense Contract Management Agency (DCMA) Memorandum of Understanding (MOU)