NASA Completes Artemis Space Launch System Structural Testing Campaign

On June 24, 2020, engineers completed the Space Launch System (SLS) rocket’s structural testing campaign for the Artemis lunar missions by testing the liquid oxygen structural test article to find its point of failure.
For the final test, the liquid oxygen tank test article — measuring 70 feet tall and 28 feet in diameter — was bolted into a massive 185,000-pound steel ring at the base of Marshall’s Test Stand 4697. Hydraulic cylinders were then calibrated and positioned all along the tank to apply millions of pounds of crippling force from all sides while engineers measured and recorded the effects of the launch and flight forces. The liquid oxygen tank circumferentially failed in the weld location as engineers predicted and at the approximate load levels expected, proving flight readiness and providing critical data for the tank’s designers. The test concluded at approximately 9 p.m. CT. This final test to failure on the LOX STA met all the program milestones.