ISS Daily Summary Report – 6/25/2020
Payloads
Radiation Dosimetry Inside ISS-Neutrons (RADI-N2): The crew retrieved all the RADIN-N2 dosimeters from the Russian crew and installed them in the Cupola. The objective of this Canadian Space Agency investigation is to better characterize the ISS neutron environment, define the risk posed to the crew members’ health, and provide the data necessary to develop advanced protective measures for future spaceflight. It’s been recognized that neutrons make up a significant fraction (10-30%) of the biologically effective radiation exposure in low-Earth orbit. The bubble detectors used in the investigation are designed to detect neutrons and ignore all other radiation.
Systems
S6 Battery Extravehicular Activity (EVA) Preparations: Today, the crew continued preparing for the S6 channel 1B battery upgrade EVA #1 by performing their equipment lock preps for Extravehicular Activity Mobility Units (EMU) 3004 and 3006. This is a continuation of the equipment lock prep started Monday. The crew also completed their EVA tool audit, and Dynamic Onboard Ubiquitous Graphics (DOUG) / Robotic Workstation (RWS) setups. Finally, the crew completed their EVA procedure reviews and participated in a pre-EVA procedure review conference. The first of the two planned S6 channel 1B battery EVAs is set for tomorrow, Friday, June 26, 2020. The crew is scheduled to egress the Quest Joint Airlock shortly after 6:40 am CT.
Completed Task List Activities:
- None
Today’s Ground Activities:
All activities are complete unless otherwise noted.
- Channel 1B battery discharge and safing (ongoing)
- Remote PCS Reboots (Cupola and Lab RWS)
- Mobile Servicing System (MSS) File Uplink
Look Ahead Plan
Friday, 6/26 (GMT 178)
Payloads:
- ISS HAM powerup and powerdowns
Systems:
- S6 1B Battery EVA#1 (Prep and EVA)
Saturday, 6/27 (GMT 179)
Payloads:
- No Payload activities
Systems:
- Post EVA PHS
- EMU Water Recharge
- EVA Procedure Review
- EVA Debrief
Sunday, 6/28 (GMT 180)
Payloads:
- Off-Duty
Systems:
- Crew Off Duty
Today’s Planned Activities:
All activities are complete unless otherwise noted.
- JEM Airlock Press & Leak Check
- ISS Crew and ГОГУ (RSA Flight Control Team) weekly conference
- UF-ATMOSFERA. PL Deactivation & Closeout Ops
- Health Maintenance System (HMS) Periodic Health Status (PHS) Pre EVA Examination
- ISS O2 repress from Progress 443 (DC1) СрПК Section 1
- Health Maintenance System (HMS) Spaceflight Cognitive Assessment Tool for Windows (WinSCAT) Test
- Station Support Computer 16 and Portable Computer System Data Acquisition System Setup
- Changeout of Replaceable Condensate Removal Lines [СМОК].
- Extravehicular Mobility Unit (EMU) Long Life Battery (LLB)/Metal Oxide (METOX) Installation
- Life on the Station Photo/Video
- Extravehicular Activity (EVA) Tool Audit
- PILLE Dosimeter Reading
- Equipment Lock (E-LK) Preparation
- PILLE sensors gathering and setup prior to USOS EVA
- USOS EVA. EVA Procedure Review
- Extravehicular Activity (EVA) Procedure Review
- Extravehicular Activity (EVA) Procedure Conference
- Visual inspection of ПН28-120 voltage converter (behind SM panel 231А).
- Portable Onboard Computers (POC) Dynamic Onboard Ubiquitous Graphics (DOUG) Setup
- Progress 448 (SM Aft) Transfers and IMS Ops
- Robotic Workstation (RWS) Setup
- Relocate PBAs for upcoming EVA
- Radiation Dosimetry Inside ISS-Neutrons Hardware Handover
- MATRYOSHKA-R. Handover of BUBBLE-dosimeters to USOS
- Extravehicular Activity (EVA) iPad Contingency Procedures preparation
- RADI-N Detector Deploy to Cupola
- MATRYOSHKA-R. BUBBLE-dosimeter initialization and deployment for exposure
- Health Maintenance System (HMS) ISS Food Intake Tracker (ISS FIT)
- Program Management/ISS Crew Conference
- ISS N2 repress from Progress 443 (DC1) СрПК Section 2