Suggested Searches

Artemis

Viewing Posts from April 2022

View All Posts

    Artemis I Update: Mission Management Team “Go” to Proceed with Tanking Pending Resolution of Gaseous Nitrogen Supply Issue 

    The mission management team chair has given a “go” to proceed  with tanking the rocket for the Artemis I  wet dress rehearsal test, pending resolution of an issue with an outage at an off-site vendor of gaseous nitrogen used inside the rocket before propellant loading. While a similar issue with a supplier of gaseous nitrogen was …

    Read Full Post

    Artemis I WDR Update: Final Umbilical Preparations Complete for Artemis I

    Final preparations on the umbilicals to ensure connectivity between the mobile launcher, the Space Launch System rocket and Orion spacecraft were completed this evening. The umbilicals provide power, communications, coolant, and fuel to different parts of the rocket. Additional accessories provide access and stabilize the rocket and spacecraft. During launch, each umbilical releases from its …

    Read Full Post

    Artemis I Update: Weather Still Favorable for Artemis I Wet Dress Rehearsal

    The mission management team for Artemis I met this morning to review the status of operations and continues to press ahead toward terminal countdown for the wet dress rehearsal test. Meteorologists with the U.S. Space Force Space Launch Delta 45 currently predict favorable weather conditions for tanking on April 14. There is currently a 5% …

    Read Full Post

    Artemis I Update: Preparations Continue, Rocket’s Core Stage Powered Up

    Overnight, launch controllers powered up the Orion spacecraft and the Space Launch System rocket’s core stage. Communications links between Orion and the Mission Control Center at Johnson Space Center in Houston were verified, and preparations of the four RS-25 engines, which will not be lit during the wet dress rehearsal, continued. Over the next several …

    Read Full Post

    Artemis I Update: Countdown is Underway for Wet Dress Rehearsal

    At approximately 5 p.m. EDT today, the launch team arrived at their stations inside the Launch Control Center at NASA’s Kennedy Space Center in Florida. The countdown will begin 30 minutes later at 5:30 p.m. or L-45 hours, 10 minutes before the initial target T-0 for the wet dress rehearsal test for NASA’s Artemis I …

    Read Full Post

    Artemis I Wet Dress Rehearsal Update 

    NASA is planning to proceed with a modified wet dress rehearsal, primarily focused on tanking the core stage, and minimal propellant operations on the interim cryogenic propulsion stage (ICPS) with the ground systems at Kennedy. Due to the changes in loading procedures required for the modified test, wet dress rehearsal testing is slated to resume …

    Read Full Post

    Artemis I Wet Dress Rehearsal Status

    In continued preparations for the Artemis I wet dress rehearsal  test, with tanking targeted for Monday, teams encountered an issue maintaining helium purge pressure on the upper stage engine after change-out of a regulator on the mobile launcher. The RL10 engine on the upper stage uses helium to purge the engine and also to activate …

    Read Full Post

    NASA Prepares for Next Artemis I Wet Dress Rehearsal Attempt

    Teams are preparing for the next attempt of the Artemis I  wet dress rehearsal, pending range availability and restoration of propellants and gases during the test. Through the past two test runs April 3 and 4, engineers accomplished several test objectives that will prepare the teams and integrated systems for launch: Configuring Launch Pad 39B …

    Read Full Post