ISS On-Orbit Status Report

Viewing Posts from August 19th 2016

View All Posts

    ISS Daily Summary Report – 08/19/2016

    U.S. Extravehicular Activity (EVA) #36: Williams (EV-1) and Rubins (EV-2) completed the following activities to install the International Docking Adapter (IDA)2 with Intravehicular (IV) support from FE-5: Pressurized Mating Adapter (PMA)-2 setup Preliminary IDA installation Initial IDA cable installation PMA-2 hemi reflector cover installation Final IDA cable installation IDA outfitting IDA cleanup IDA3 cable routing …