    Engineers Troubleshooting Engine Conditioning Issue

    Artemis Logo - red rocket trail, blue arch that represents earth, ARTEMIS text, gray half sphere on a white background

    While liquid oxygen loading into the interim cryogenic propulsion stage continues and core stage tanks continue to be replenished with propellants, engineers are troubleshooting an issue conditioning one of the RS-25 engines (engine 3) on the bottom of the core stage. Launch controllers condition the engines by increasing pressure on the core stage tanks to …

    Read Full Post

    Core Stage Fueling in Replenish, Go for Upper Stage LOX Loading

    Artemis Logo - red rocket trail, blue arch that represents earth, ARTEMIS text, gray half sphere on a white background

    The Space Launch System’s core stage liquid oxygen (LOX) and liquid hydrogen (LH2) tanks are fully fueled and both are being replenished. During replenish, the propellant that naturally boils off is being replaced to ensure the tanks are at full capacity for launch. A “go” has been given for liquid oxygen loading into the interim …

    Read Full Post

    Core Stage Propellant Loading Continues, Teams Go for Upper Stage Tanking

    Artemis Logo - red rocket trail, blue arch that represents earth, ARTEMIS text, gray half sphere on a white background

    As teams continue to fuel the Space Launch System (SLS) rocket’s core stage with liquid oxygen (LOX) and liquid hydrogen (LH2), teams have been given a go to begin propellant loading operations for the rocket’s interim cryogenic propulsion stage (ICPS). The ICPS is the upper stage of the rocket responsible for giving the Orion spacecraft the …

    Read Full Post

    Engineers Troubleshoot Core Stage Liquid Hydrogen Leak in Mating Interface

    Artemis Logo - red rocket trail, blue arch that represents earth, ARTEMIS text, gray half sphere on a white background

    During the transition from slow fill of liquid hydrogen into the Space Launch System rocket’s core stage to fast fill operations, launch controllers saw a spike in the amount of hydrogen that is allowed to leak into the purge can, a housing covering the tail service mast umbilical’s quick disconnect, or mating interface with the …

    Read Full Post

    Core Stage Propellant Loading Underway  

    Artemis Logo - red rocket trail, blue arch that represents earth, ARTEMIS text, gray half sphere on a white background

    After chilling the lines for liquid oxygen (LOX) and beginning with slow fill of the Space Launch System (SLS) rocket’s core stage, the team has now transitioned to LOX fast fill. Teams have also completed chilldown of the liquid hydrogen (LH2) lines and started LH2 slow fill.  

    Read Full Post

    NASA TV Coverage Underway, Propellant Loading on Hold Due to Weather 

    Artemis Logo - red rocket trail, blue arch that represents earth, ARTEMIS text, gray half sphere on a white background

    The launch team is ready to begin loading propellant into the rocket, but they are holding due to a small weather cell that is producing lighting. Weather criteria for tanking stipulate that the probability of lightning must not exceed 20% in the first hour of tanking. The team is prepared to proceed with tanking as soon as …

    Read Full Post

    Mission Management Team “Go” to Proceed With Tanking for Artemis I Mission

    Artemis Logo - red rocket trail, blue arch that represents earth, ARTEMIS text, gray half sphere on a white background

    The Artemis I Mission Management Team has given the “go” to proceed toward tanking operations. Weather conditions remain 80% favorable at the beginning of the two-hour launch window which opens at 8:33 a.m. EDT Aug. 29, with chances for rain showers increasing toward the later part of the window. Artemis I launch director Charlie Blackwell-Thompson …

    Read Full Post

    Artemis I Update: Rocket’s Upper Stage Powered Up, Countdown on Track

    Artemis Logo - red rocket trail, blue arch that represents earth, ARTEMIS text, gray half sphere on a white background

    The Space Launch System rocket’s interim cryogenic propulsion stage (ICPS) has been powered up, the NASA test director has given the “go” for booster power up, and all non-essential personnel have left the launch pad area in preparation for propellant loading operations. At 10:53 p.m. EDT, or L-9 hours, 40 minutes, the launch team is …