SLS Core Stage Production Continues for Rocket’s First Flight

Throughout NASA’s 43-acre rocket factory, the Michoud Assembly Facility in New Orleans, engineers are building all five parts of the Space Launch System’s core stage. For the first SLS flight for deep space exploration with NASA’s Orion spacecraft, major structural manufacturing is complete on three parts: the forward skirt, the intertank and the engine section. Test articles, which are structurally similar to flight hardware, and are used to qualify the core stage for flight, are in various stages of production and testing.

NASA Clears Liquid Oxygen Dome for Use in SLS Test Article
NASA cleared the dome, shown here being removed from the infeeder tool, for use as intended as the bottom dome of the liquid oxygen tank structural test article being welded in the Vertical Assembly Center, right. The dome sustained minor damage during operations May 3, 2017. The investigation team is currently wrapping up their investigation of the mishap and will prepare recommendations to the SLS program.
NASA/MAF/Judy Guidry

“One of the most challenging parts of building the world’s most powerful rocket has been making the largest rocket stage ever manufactured for the first time,” said Steve Doering, the SLS stages manager at NASA’s Marshall Space Flight Center in Huntsville, Alabama. “The 212-foot-tall core stage is a new design made with innovative welding tools and techniques.”

To build the rocket’s fuel tanks, Boeing, the prime contractor for the SLS core stage, is joining some of the thickest parts ever built with self-reacting friction stir welding. NASA and Boeing engineers and materials scientists have scrutinized the weld confidence articles and developed new weld parameters for making the liquid oxygen and hydrogen tanks for the first SLS mission.

Engineers Prepare to Resume Welding SLS Test Article
NASA and Boeing have cleared the dome, shown here, for use as the bottom of dome of a SLS liquid oxygen tank structural test article. After the dome is welded to the rest of the test article in the Vertical Assembly Center, right, it will undergo inspection and processing before being shipped from the Michoud Assembly Facility in New Orleans to NASA’s Marshall Space Flight Center in Huntsville, Alabama, for structural testing.
NASA/MAF/Judy Guidry

Resuming Welding in the Vertical Assembly Center

The Vertical Assembly Center, the large robotic tool where core stage parts are welded to form major structures, is expected to resume manufacturing next week. NASA halted production in early May after a liquid oxygen tank dome was inadvertently damaged during pre-weld preparations on the infeeder tool. This equipment is what positions the large dome for welding, or feeds it into the tank.

While the mishap investigation is still wrapping up, NASA and Boeing fully inspected the impacted dome and found while the hardware sustained minor damage, it is usable for its original purpose as part of a structural test article. The infeeder tool did sustain some damage during the incident and repairs to the tool are complete. Welding is resuming to finish construction of the liquid oxygen test article by adding the aft, or bottom, dome. Upon completion, the tank will undergo inspection for any flaws, final processing and proof testing.

SLS Interank Completes Structural Assembly
Engineers assembled the structure of the intertank that will be flown on the first Space Launch System integrated flight with Orion. The intertank, one of five parts of the 212-foot core stage being built and assembled at NASA’s Michoud Assembly Facility in New Orleans, is on its way to undergo the application of thermal protection systems. The intertank is the only major structural part of the core stage that is not welded. It is made of eight large panels which are connected with 7,500 bolts. The 22-foot-tall structure carries most of the massive launch load produced by the solid rocket boosters that separate from the core stage about two minutes after launch.
NASA/MAF/Judy Guidry

In another area of the factory, domes and segments for the flight liquid oxygen tank await their turn to be joined on the VAC, and Boeing is now completing welding domes and barrels that will make up the liquid hydrogen tank for flight. Recently, major structural construction was completed on flight hardware for the one part of the core stage structure not welded. The intertank walls are too thick to be welded, so its eight panels are connected with 7,500 bolts. The walls have to be extremely strong because of the force it feels from the solid rocket boosters attached to it. To complete assembly on the inside of the core stage, the team is outfitting the intertank along with the flight forward skirt and the engine section structures, with avionics, wire harnesses, tubing, sensors, and propulsion systems.

Progress Continues on SLS Core Stage Hardware for First Flight
The Space Launch System intertank, shown here moving down the factory floor, finished structural assembly at NASA’s Michoud Assembly Facility in New Orleans. Technicians moved it to an area where it will be coated with a thermal protection system. The yellow object, left back, is the engine section of the core stage, which also completed structural assembly and is being outfitted with propulsion system hardware that will feed fuel to the four RS-25 engines on the first SLS mission.
NASA/MAF/Judy Guidry

Preparing Hardware for Testing

NASA and Boeing continue to prepare existing hardware for tests to help ensure success of the first SLS flight and crew safety on future missions. Before the tanks are hooked up to feed propellant to the four RS-25 engines or through a test stand propellant system, the tanks have to be cleaned to avoid any contamination. Though the liquid hydrogen structural test article is not fueled, the tank has recently been moved to the cleaning cell to certify the process ahead of the flight tank. 

SLS Liquid Hydrogen Tank Test Article Prepares for a “Shower”
More than 500,000 gallons of fuel will flow from the liquid hydrogen tank to the four RS-25 engines that power NASA’s Space Launch System rocket. During flight, and even during testing, a tank’s insides must be clean to ensure contaminants do not find their way into complex propulsion and engine systems. Technicians recently lifted the liquid hydrogen tank structural qualification test article into a cleaning cell at NASA’s Michoud Assembly Facility in New Orleans where its insides will be thoroughly cleaned, coated and dried to certify the process for the following flight article.
NASA/MAF/Judy Guidry

The first structural test article for SLS, an engine section which is similar to the flight article located at the bottom of the rocket’s core stage, is being installed on a test stand at NASA’s Marshall Space Flight Center in Huntsville, Alabama. Hydraulic cylinders will push, pull, twist and bend the engine test article to validate the design and ensure it can withstand the pressure expected during launch and ascent.

“We are conducting the largest NASA launch vehicle test campaign since space shuttle development,” said John Honeycutt, the SLS program manager at Marshall. “The team is focused on delivering hardware to the pad for the first launch. We just completed integrated structural testing for the stage that will send Orion out beyond the moon on the first flight. Now, we’ll be putting the core stage parts through the paces to gain an in-depth understanding of the rocket we are building for the first time as we expose parts of it to the extreme conditions of spaceflight.”

Technicians Prepare to Clean Rocket Fuel Tank
The bottom of a Space Launch System liquid hydrogen fuel tank test article is visible as it is lowered into a cleaning cell at NASA’s Michoud Assembly Facility in New Orleans where the tank was manufactured. Technicians will clean the inside of the tank to remove any potential contaminants.
NASA/MAF/Judy Guidry