Public Lessons Learned Entry: 1031

Lesson Info:

  • Lesson Number: 1031
  • Lesson Date: 2001-07-20
  • Submitting Organization: DFRC
  • Submitted by: Roy Tryon

Subject:

Construction Site Safety, Insulation Impaling Pins

Description of Driving Event:

DFRC B4822

Incident Report: A workman was on a ladder spray painting alongside a sheet metal panel wall which had previously been insulated with large continuous insulation batts. The insulation was installed on impaling pins about 1/8" x 8" long. The insulation crew had not trimmed or nipped off the excess projecting pins, leaving 2 to 3 inches projecting from the wall. The painter dropped a can or tool and he lunged to catch it. The ladder shifted abruptly. He instinctively put out his hand to steady his situation and impaled his hand on one of the projecting pins. When he pulled his hand off of the pin, he suffered profuse arterial bleeding.

The medical team responded quickly, and the painter's wound was treated and bandaged at the site. The area required a blood clean-up. The workman was sent home that afternoon, but returned to work the next morning.

Lesson(s) Learned:

  1. Impaling pins present a jobsite hazard.
  2. Working around impaling pins requires extra care and proper equipment.
  3. Activity hazard analysis for all on-going work must be reviewed with ALL trades on a daily basis.

Recommendation(s):

  1. Use a more stable ladder for high work.
  2. Use a safer, more stable, roll-around scaffold when hazardous pins are present.
  3. Cut off and trim all impaling pins prior to other adjacent contract operations.
  4. Consider using other insulation support methods instead of impaling pins.
  5. Modify Specifications to include "prompt nipping, trimming and safing of projecting impaling pins."
  6. When pins are present, include impaling pin hazards in daily safety meetings and in activity hazard analysis.

Evidence of Recurrence Control Effectiveness:

N/A

Documents Related to Lesson:

N/A

Mission Directorate(s):

  • Exploration Systems
  • Aeronautics Research

Additional Key Phrase(s):

  • Environment
  • Facilities

Additional Info:

    Approval Info:

    • Approval Date: 2001-12-05
    • Approval Name: John Marcrum
    • Approval Organization: DFRC
    • Approval Phone Number: 661-276-2825


    FirstGov - Your First Click to the US Government
    + 2004 Vision for Space Exploration
    + FY 2005 Budget Request
    + 2003 Strategic Plan
    + Freedom of Information Act
    + The President's Management Agenda
    + FY 2003 Agency Performance and Accountability Report
    + NASA Privacy Statement, Disclaimer,
    and Accessibility Certification

    + Freedom to Manage
    NASA
    Curator:Manson Yew
    NASA Official: Gregory Robinson
    + Contact LLIS