NASA ENGINEERING NETWORK
Follow this link to skip to the main content
+ Contact LLIS
Go
ABOUT NASALATEST NEWSMULTIMEDIAMISSIONSMyNASAWORK FOR NASA

+ NASA Home
FIND ENGINEERING RESOURCES BY
LLIS HOME
NASA CENTERS
MISSION DIRECTORATE
TOPICS
BY YEAR


Public Lessons Learned Entry: 0655

Lesson Info:

  • Lesson Number: 0655
  • Lesson Date: 1999-02-01
  • Submitting Organization: JPL
  • Submitted by: Wil Harkins

Subject:

Preliminary Design Review

Abstract:

Preferred Practice for Design & Test. One or more potential problems that could result in an adverse impact on the system, subsystem, or project might not be identified in a timely manner. This oversight might later result in a condition having a significant effect on quality, reliability, capability, schedule, or cost. Conduct a formal Preliminary Design Review (PDR) at the system and subsystem levels prior to the start of subsystem detail design, to assure that the proposed design and associated implementation approach will satisfy the system and subsystem functional requirements.

Description of Driving Event:

This Lessons Learned is based on Reliability Practice No. PD-ED-1215.1; from NASA Technical Memorandum 4322A, NASA Reliability Preferred Practices for Design and Test.

Benefits:

The Preliminary Design Review (PDR) will provide for increased assurance that the proposed design approach, and the manufacturing and test implementation plans, will result in an acceptable product, with minimal project risk.

Implementation Method:

The responsible project/task manager defines the need for, and initiates the action for conducting a formal review by contacting the convening authority (generally the next higher management level). The convening authority, in consultation with the responsible manager, appoints the review board and a chair, and defines the board charter and schedule.

The review board, under direction of the chair, will conduct the review, and will prepare a written report to the responsible manager of the findings and recommendations. The board may elect to use the JPL Recommendation For Action form (RFA) to document recommendations, which are advisory and are not direction to the manager. The responsible manager will prepare a written response to the convening authority addressing the disposition of the review board findings and recommendations for action. The convening authority will review and approve these dispositions.

PDR Agenda. The following items and issues should be addressed at the PDR. (It should be noted that all items may not apply in all cases, and that additional items may apply in some cases.)

  1. Functional description and block diagram
  2. Functional requirements and compliance of the design
  3. Subassembly/subsystem Functional Requirements Review Action Items and disposition
  4. Accuracy requirements and compliance of the design
  5. Interface requirements and compliance of the design
  6. Mass requirements and compliance of the design
  7. Memory requirements and compliance of the design
  8. Environmental requirements and compliance of the design
  9. Project single point failure (SPF) policy and compliance of the design
  10. Reliability requirements and compliance of the design
  11. Safety requirements and compliance of the design
  12. Maintainability requirements and compliance of the design
  13. Electronic piecepart requirements and compliance of the design
  14. Make or buy decision and rationale
  15. Inherited hardware/software and compliance with project requirements
  16. Spares requirements and plans for compliance
  17. Quality Assurance requirements and plans for compliance
  18. Software Assurance requirements and plans for compliance
  19. Reliability analyses requirements and plans for compliance
  20. Safety analyses requirements and plans for compliance
  21. Documentation requirements and plans for compliance
  22. Support equipment requirements and plans for compliance
  23. Structural analysis requirements and plans for compliance
  24. Thermal analyses requirements and plans for compliance
  25. Calibration requirements and plans for compliance
  26. Testability requirements and plans for compliance
  27. Qualification test requirements and plans for compliance
  28. Acceptance test requirements and plans for compliance
  29. Development schedule and constraints
  30. Long-lead parts requirements and procurement plans
  31. Manufacturing and test facility requirements, availability, and acceptability
  32. Environmental test facility requirements, availability, and acceptability
  33. Hazardous operations facility requirements, availability, and acceptability

The PDR allows for an assessment of the design and plans by a group of knowledgeable persons not directly involved in the activity being reviewed. A formal review can focus many years of experience on the subject at hand.

Technical Rationale:

The PDR aids the responsible manager in evaluating the quality of the work, and in making important decisions, including those concerning completion of critical milestones. The review process should aid in the identification of problems, and the evaluation of design approaches and options.

References:

  1. JPL Standard Practice Instruction (SPI) 4-16-1.
  2. JPL D-363 Guidelines for Planning and Conducting Formal Reviews.

Lesson(s) Learned:

Impact of Nonpractice:

One or a number of potential problems which could result in an adverse impact on the system, subsystem, and/or project might not be identified in a timely manner. This oversight might later result in a condition having a significant effect on quality, reliability, capability, schedule, and/or cost.

Recommendation(s):

Practice:

Conduct a formal Preliminary Design Review (PDR) at the system and subsystem levels prior to the start of subsystem detail design, to assure that the proposed design and associated implementation approach will satisfy the system and subsystem functional requirements.

Evidence of Recurrence Control Effectiveness:

Programs that Certified Usage:

The PDR process has been used on all JPL-managed projects and science instrument tasks, including Ranger, Mariner, Voyager, Galileo, Magellan, Topex/Poseidon, MLS, WFPC, and numerous other science instrument tasks.

Documents Related to Lesson:

N/A

Mission Directorate(s):

  • Exploration Systems
  • Science
  • Space Operations
  • Aeronautics Research

Additional Key Phrase(s):

  • Aircraft
  • Configuration Management
  • Facilities
  • Flight Operations
  • Flight Equipment
  • Ground Operations
  • Ground Equipment
  • Hardware
  • Launch Process
  • Launch Vehicle
  • Lifting Devices
  • Payloads
  • Research & Development
  • Risk Management/Assessment
  • Safety & Mission Assurance
  • Software
  • Spacecraft
  • Test Article
  • Test Facility
  • Test & Verification
  • Training Equipment

Additional Info:

    Approval Info:

    • Approval Date: 2000-03-03
    • Approval Name: Eric Raynor
    • Approval Organization: QS
    • Approval Phone Number: 202-358-4738


    FirstGov - Your First Click to the US Government
    + 2004 Vision for Space Exploration
    + FY 2005 Budget Request
    + 2003 Strategic Plan
    + Freedom of Information Act
    + The President's Management Agenda
    + FY 2003 Agency Performance and Accountability Report
    + NASA Privacy Statement, Disclaimer,
    and Accessibility Certification

    + Freedom to Manage
    NASA
    Curator:Celeste Merryman
    NASA Official: Gregory Robinson
    + Contact LLIS