| | 09.11.06 - STS-115 MCC Status Report #04
The Space Shuttle Atlantis crew has begun a busy and exciting day. The shuttle and the International Space Station are scheduled to dock at 5:46 a.m. CDT and begin seven days of joint operations.
+ Read More | |
 |
| | 09.10.06 - STS-115 MCC Status Report #03
It was a productive day for the six astronauts onboard Atlantis. The crew inspected the shuttle's heat shield, prepared for docking to the International Space Station and readied spacesuits for the upcoming three spacewalks.
+ Read More | |
 |
| | 09.10.06 - STS-115 MCC Status Report #02
After days of waking up in quarantine, the crew of the space shuttle Atlantis woke up in weightlessness for its first full day in space.
+ Read More | |
 |
| | 09.09.06 - STS-115 MCC Status Report #01
Atlantis launched into an almost clear Florida sky this morning for an 11-day mission that marks the return to assembly of the International Space Station.
+ Read More | |
 |
| | 09.05.06 - Space Shuttle Processing Status Report
At Launch Pad 39B, preparations for Wednesday's launch of Space Shuttle Atlantis on mission STS-115 are under way. The external tank camera functional test is complete.
+ Read More | |
 |
| | 09.04.06 - Space Shuttle Processing Status Report
At Launch Pad 39B, preparations for Wednesday's launch of Space Shuttle Atlantis on mission STS-115 are under way. The launch countdown began on Sunday at 8 a.m.
+ Read More | |
 |
| | 09.01.06 - Space Shuttle Processing Status Report
At Launch Pad 39B, preparations for Wednesday's launch of Space Shuttle Atlantis are under way, with the launch countdown scheduled to begin on Sunday at 8 a.m.
+ Read More | |
 |
| | 08.26.06 - Space Shuttle Processing Status Report
The Mission Management Team decided today to postpone the launch of Atlantis for 24 hours. Launch is now scheduled for 4:04 p.m. Eastern time on Monday, Aug. 28.
+ Read More | |
 |
| | 08.25.06 - Space Shuttle Processing Status Report
Atlantis' payload bay doors were closed for flight last night, and loading of the fuel for the power reactant storage and distribution system is now under way.
+ Read More | |
 |
| | 08.24.06 - Space Shuttle Processing Status Report
Closeout of Atlantis' aft compartments is complete. Technicians have finished performing the aft confidence test, which involves powering up and testing all of the aft systems.
+ Read More | |
 |
| | 08.23.06 - Space Shuttle Processing Status Report
Closeout of Atlantis' aft compartments continues, with aft door installation expected later today. Once the doors are installed, workers will begin aft confidence testing.
+ Read More | |
 |
| | 08.22.06 - Space Shuttle Processing Status Report
Closeout of the orbiter's aft compartments continues, and pressurization of the orbiter's maneuvering system, reaction control system and main propulsion system is under way.
+ Read More | |
 |
| | 08.21.06 - Space Shuttle Processing Status Report
Following a decision to replace two Ku-band antenna actuator bolts in Atlantis' payload bay, workers spent the weekend successfully performing the bolt replacement.
+ Read More | |
 |
| | 08.16.06 - Space Shuttle Processing Status Report
At Launch Pad 39B, functional tests and checkout of the shuttle and pad systems continue. Hypergolic propellant loading continues and should be complete by Thursday.
+ Read More | |
 |
| | 08.14.06 - Space Shuttle Processing Status Report
At Launch Pad 39B, functional tests and checkout of the Space Shuttle Atlantis and pad systems are under way. Hypergolic propellant loading continues this week.
+ Read More | |
 |