NASA NEWS

Katherine Trinidad
Headquarters, Washington
(Phone: 202/358-3749)

George H. Diller
Kennedy Space Center, Fla.
(Phone: 321/867-2468)


June 29, 2005
STATUS REPORT: E05-005

NASA Expendable Launch Vehicle Status Report: E05-005

Mission: Mars Reconnaissance Orbiter (MRO)
Launch Vehicle: Lockheed Martin Atlas V 401
Launch Pad: Space Launch Complex 41 (SLC-41), Cape Canaveral Air Force Station (CCAFS), Fla.
Launch Date: August 10, 2005
Launch Window: 7:53:58 to 9:53:58 a.m. (EDT)

Power-on testing continues to go well. The high-gain antenna was installed on June 24. The solar arrays have been cleaned, inspected and installed. This week, the solar arrays will be deployed, inspected and stowed for launch.

The Centaur upper stage for the Atlas V is at the Vertical Integration Facility (VIF) at SLC-41. It was hoisted atop the Atlas stage to begin checkout.

The Launch Vehicle Readiness Test continues. A countdown wet dress rehearsal with the launch vehicle fully fueled is scheduled for early July.

The MRO will be transported from the Payload Hazardous Servicing Facility at KSC to the VIF in late July. It will join the Atlas V for the final phase of launch preparations. The spacecraft will undergo a functional test, a final week of integrated testing and closeouts.

The MRO mission is managed by NASA's Jet Propulsion Laboratory, a division of the California Institute of Technology in Pasadena, Calif., for the agency's Science Mission Directorate. Lockheed Martin Space Systems is the prime contractor for the project and will provide launch services for the mission with International Launch Services.

Mission: Cloud-Aerosol Lidar & Infrared Pathfinder Satellite Observation and CloudSat (CALIPSO/CloudSat)
Launch Vehicle: Boeing Delta II 7420 DPAF
Launch Pad: Space Launch Complex 2 (SLC2), Vandenberg Air Force Base (VAFB), Calif.
Launch Date: No Earlier Than August 22, 2005

CloudSat completed battery reconditioning late Monday. Technicians are also performing some additional spacecraft testing. Stacking of the Boeing Delta II at SLC-2 and attachment of the four strap-on solid rocket boosters is complete.
Previous status reports are available on the Internet at:

http://www.nasa.gov/centers/kennedy/launchingrockets/status/2005

For information about NASA and agency programs on the Internet, visit:

http://www.nasa.gov/home/index.html



- end -


text-only version of this release

NASA press releases and other information are available automatically by sending a blank e-mail message to hqnews-subscribe@mediaservices.nasa.gov. To unsubscribe from this mailing list, send a blank e-mail message to hqnews-unsubscribe@mediaservices.nasa.gov.

Back to NASA Newsroom | Back to NASA Homepage

+ Back to Top
FirstGov - Your First Click to the US Government

ExpectMore.gov

+ Freedom of Information Act
+ Budgets, Strategic Plans and Accountability Reports
+ The President's Management Agenda
+ NASA Privacy Statement, Disclaimer,
and Accessibility Certification

+ Inspector General Hotline
+ Equal Employment Opportunity Data Posted Pursuant to the No Fear Act
+ Information-Dissemination Priorities and Inventories
NASA
Editor: Linda Lynch
NASA Official: Brian Dunbar
Last Updated: April 23, 2006
+ Contact NASA
+ SiteMap