May 28, 2004
 
RELEASE : S04-13
 
 
Space Shuttle Processing Status Report: S04-13
 
 
The Space Shuttle fleet is housed and processed at NASA's Kennedy Space Center (KSC), Fla. The order the Space Shuttles are listed in this report does not necessarily reflect the chronological order of future missions.

Discovery (OV-103)

Technicians continue to process Discovery in the Orbiter Processing Facility (OPF) for its Return to Flight mission, STS-114, to the International Space Station. Vehicle power up work continues with Orbiter Maneuvering System pod thruster installations, an Air Data Probe leak test, Main Propulsion System actuator and latch system leak checks, and S-band communications system checks.

As early as next week, Discovery will enter a month-long power down period in which modifications will be made for Return to Flight. Modifications include wiring that will support the addition of the boom sensor system and installation of the wing leading-edge sensors.

Atlantis (OV-104)

In the OPF, processing continues on Atlantis in preparation for its future flight to the International Space Station. Today, Atlantis will begin a four-month power down period for modifications including detailed wire inspections, wiring that will support the addition of the boom sensor system, and installation of the wing leading-edge sensors.

Structural and baseline wire inspections, as well as preparations for Freon Coolant Loop No. 2 deservicing, are in progress. Left-hand Reinforced Carbon-Carbon panel installation is complete, and all but one of the left-hand T-seals have been installed on the vehicle.

Endeavour (OV-105)

Space Shuttle Endeavour is in its Orbiter Major Modification period, which began in December. Electrical modifications continue in the crew module. Wire inspections are ongoing in the Environmental Control and Life Support System bay.

Three of the four right-hand radiators are installed on the vehicle, with the final radiator to be installed next week. Thermal Control System blanket work continues in support of the first two left-hand payload bay door radiators, which are scheduled to be installed next week. Bead blasting of Endeavour's wing leading edge is ongoing in support of reinstalling the RCC panels and associated fittings.

Previous Space Shuttle processing status reports are available on the Internet at:

http://space.mit.edu/HETE/

For information about NASA's Return to Flight efforts on the Internet, visit:

http://www.nasa.gov

For information about NASA and agency programs on the Internet, visit:

http://www.nasa.gov

 

- end -


text-only version of this release

NASA press releases and other information are available automatically by sending a blank e-mail message to hqnews-subscribe@mediaservices.nasa.gov. To unsubscribe from this mailing list, send a blank e-mail message to hqnews-unsubscribe@mediaservices.nasa.gov.

Back to NASA Newsroom | Back to NASA Homepage