The Space Shuttle fleet is housed and processed at NASA's Kennedy Space Center (KSC), Fla. The order of the Space Shuttles in this report does not necessarily reflect the chronological order of future missions.

Discovery (OV-103)

Processing continues in the Orbiter Processing Facility in preparation for Discovery's Return to Flight mission, STS-114, to the International Space Station. Vehicle power-up work continues with Orbital Maneuvering System pod continuity checks and verification testing.

Following the installation of the four new Rudder Speed Brake (RSB) actuators, technicians continue to re-hang the four panels. On Tuesday, workers completed the installation of Discovery's external airlock and hung the first Reinforced Carbon-Carbon (RCC) panel on the right-hand leading edge of the wing.

Atlantis (OV-104)

Atlantis was powered up in support of mission processing for its future flight to the International Space Station. Fuel cell removal began on Monday.

The four RSB panels and actuators were removed from the vehicle. The actuators will be X-rayed to determine whether the gears were assembled in the proper orientation. When completed, they will be sent to the vendor for a complete inspection. Left-hand RCC panel installation is complete. Twenty right-hand panels have been assembled prior to being hung.

Endeavour (OV-105)

Space Shuttle Endeavour is still in the Orbiter Major Modification (OMM). The OMM began in December 2003. Electrical modifications continue in the crew module. Wire inspections on Endeavour are complete in all areas except the Environmental Control and Life Support System bay. Inspections are in process in that bay.

Technicians continue to bond Thermal Protection System tiles to the External Tank door. Right-hand radiators No. 3 and 4 arrived in the Orbiter Processing Facility and were installed on the vehicle.

Previous Space Shuttle processing status reports are available on the Internet at:

http://www-pao.ksc.nasa.gov/kscpao/status/status.htm

For information about NASA's Return to Flight efforts on the Internet, visit:

http://www.nasa.gov/news/highlights/returntoflight.html

For information about NASA and agency programs on the Internet, visit:

http://www.nasa.gov

 

- end -


text-only version of this release

NASA press releases and other information are available automatically by sending a blank e-mail message to hqnews-subscribe@mediaservices.nasa.gov. To unsubscribe from this mailing list, send a blank e-mail message to hqnews-unsubscribe@mediaservices.nasa.gov.

Back to NASA Newsroom | Back to NASA Homepage