August 13, 2004
 
RELEASE : S04-027
 
 
Space Shuttle Processing Status Report: S04-027
 
 
The Space Shuttle fleet is housed and processed at NASA's Kennedy Space Center (KSC), Fla. The order the Space Shuttles are listed in this report does not necessarily reflect the chronological order of future missions.

Discovery (OV-103)

Following the Return to Flight modifications performed on Discovery during its power-down period, work on the orbiter is returning to a more normal processing flow in preparing for its future mission to the International Space Station. Freon coolant loop No. 2 was serviced this week, including the successful completion of leak checks. The final stage of Rudder Speed Brake panel installation continues.

Due to the impending arrival of Hurricane Charley, which was expected to affect the Kennedy Space Center area today, much of the normal workflow was inhibited on Wednesday and Thursday while employees prepared the vehicles, equipment and buildings for the storm.

Atlantis (OV-104)

Atlantis is in a four-month power-down period, and the critical path wiring inspections and Return to Flight electrical modifications continue on schedule.

The right-hand Orbital Maneuvering System main engine was installed. Water coolant loop No. 1 has been drained and X-rays completed. The main landing gear was lowered for technicians to perform checks and optical measurements to ensure the landing gear will perform properly during the mission. Workers also began checkout of the nose cap, including temperature and impact sensor instrumentation.

Endeavour (OV-105)

Space Shuttle Endeavour is in its Orbiter Major Modification period, which began in December. Electrical modifications continue in the crew module. The Flash Evaporator System, which helps to cool the vehicle while in flight, was installed in the aft of the orbiter.

Three String Global Positioning System wire routing in the avionics bay and flight deck continues. The temporary installation of the nose cap is complete. The chin panel, which is the semicircle-shaped piece of Reinforced Carbon-Carbon insulation under the nose cap, is undergoing a fit-check.

 

- end -