Follow this link to go to the text only version of nasa.gov
NASA -National Aeronautics and Space Administration
Follow this link to skip to the main content
+ Text Only Site
+ Site Help & Preferences
Go
ABOUT NASALATEST NEWSMULTIMEDIAMISSIONSMyNASAWORK FOR NASA

+ NASA Home
+ KSC Home
Kennedy Space Center
CENTER HOME
ABOUT KENNEDY
KENNEDY NEWS
KENNEDY MULTIMEDIA
MISSIONS
KENNEDY EVENTS
EDUCATION
DOING BUSINESS WITH US
SHUTTLE OPERATIONS
LAUNCHING ROCKETS
STATION PAYLOADS
Go
+ NASA Home > Centers > Kennedy Space Center > Shuttle Operations > Shuttle Status Reports > 2004
Print ThisPrint This
Email ThisEmail This

NASA NEWS

Allard Beutel
Headquarters, Washington
(Phone: 202/358-4769)

Jessica Rye
Kennedy Space Center, Fla.
(Phone: 321/867-2468)


Oct. 22, 2004
RELEASE: S04-035

Space Shuttle Processing Status Report: S04-035

The Space Shuttle fleet is housed and processed at NASA's Kennedy Space Center (KSC), Fla. The order the Space Shuttles are listed in this report does not necessarily reflect the chronological order of future missions.

Discovery (OV-103)

In the Orbiter Processing Facility, technicians continue to perform system testing for Discovery's Return to Flight mission, designated STS-114, to the International Space Station.

The Remote Manipulator System (RMS), or Space Shuttle robotic arm, was installed in the payload bay on Oct. 15. The arm was powered up for testing on Wednesday. During testing, the end effector, or grappling end, saw an unexpected temperature increase. Managers have decided to remove the end effector and replace it. The RMS will not have to be removed to perform this work.

Atlantis (OV-104)

Atlantis will be powered up the week of Nov. 15, following an extensive power-down period during which Return to Flight modifications are being performed. These included the wiring for the Orbiter Boom Sensor System and installation of the wing leading edge sensors.

All four right-hand and left-hand radiators have been installed for flight. Close out of the chin panel, the semi-circle-shaped section of Reinforced Carbon-Carbon under the nose cap, is ongoing. Technicians continue critical path wiring, structural inspections and electrical modifications throughout the vehicle.

Endeavour (OV-105)

Space Shuttle Endeavour is in its Orbiter Major Modification period, which began in December 2003. Electrical modifications continue in the crew module. Three-String Global Positioning System wire routing in the avionics bay and flight deck continues.

Technicians are beginning elevon actuator inspections. Removal of the left outboard elevon actuator is complete. Once the actuator was removed, leak and flow checks were performed. Reinstallation is scheduled for tomorrow.

Previous Space Shuttle processing status reports are available on the Internet at:

http://www-pao.ksc.nasa.gov/kscpao/status/status.htm

For information about NASA's Return to Flight efforts on the Internet, visit:

http://www.nasa.gov/news/highlights/returntoflight.html

For information about NASA and agency programs on the Internet, visit:

http://www.nasa.gov



- end -


text-only version of this release

To receive status reports and news releases issued from the Kennedy Space Center Newsroom electronically, send a blank e-mail message to ksc-subscribe@newsletters.nasa.gov. To unsubscribe, send a blank e-mail message to ksc-unsubscribe@newsletters.nasa.gov. The system will confirm your request via e-mail.

+ Back to Top
FirstGov - Your First Click to the US Government

ExpectMore.gov

+ Freedom of Information Act
+ Budgets, Strategic Plans and Accountability Reports
+ The President's Management Agenda
+ Privacy Policy and Important Notices
+ Inspector General Hotline
+ Equal Employment Opportunity Data Posted Pursuant to the No Fear Act
+ Information-Dissemination Priorities and Inventories
NASA
Editor: Linda Lynch
NASA Official: Brian Dunbar
Last Updated: January 5, 2007
+ Contact Kennedy
+ SiteMap