Follow this link to go to the text only version of nasa.gov
NASA -National Aeronautics and Space Administration
Follow this link to skip to the main content
+ Text Only Site
+ Site Help & Preferences
Go
ABOUT NASALATEST NEWSMULTIMEDIAMISSIONSMyNASAWORK FOR NASA

+ NASA Home
+ KSC Home
Kennedy Space Center
CENTER HOME
ABOUT KENNEDY
KENNEDY NEWS
KENNEDY MULTIMEDIA
MISSIONS
KENNEDY EVENTS
EDUCATION
DOING BUSINESS WITH US
SHUTTLE OPERATIONS
LAUNCHING ROCKETS
STATION PAYLOADS
Go
+ NASA Home > Centers > Kennedy Space Center > Shuttle Operations > Shuttle Status Reports > 2004
Print ThisPrint This
Email ThisEmail This

NASA NEWS

Melissa Mathews
Headquarters, Washington
(Phone: 202/358-1272)

August 13, 2004
RELEASE: S04-027

Space Shuttle Processing Status Report: S04-027

The Space Shuttle fleet is housed and processed at NASA's Kennedy Space Center (KSC), Fla. The order the Space Shuttles are listed in this report does not necessarily reflect the chronological order of future missions.

Discovery (OV-103)

Following the Return to Flight modifications performed on Discovery during its power-down period, work on the orbiter is returning to a more normal processing flow in preparing for its future mission to the International Space Station. Freon coolant loop No. 2 was serviced this week, including the successful completion of leak checks. The final stage of Rudder Speed Brake panel installation continues.

Due to the impending arrival of Hurricane Charley, which was expected to affect the Kennedy Space Center area today, much of the normal workflow was inhibited on Wednesday and Thursday while employees prepared the vehicles, equipment and buildings for the storm.

Atlantis (OV-104)

Atlantis is in a four-month power-down period, and the critical path wiring inspections and Return to Flight electrical modifications continue on schedule.

The right-hand Orbital Maneuvering System main engine was installed. Water coolant loop No. 1 has been drained and X-rays completed. The main landing gear was lowered for technicians to perform checks and optical measurements to ensure the landing gear will perform properly during the mission. Workers also began checkout of the nose cap, including temperature and impact sensor instrumentation.

Endeavour (OV-105)

Space Shuttle Endeavour is in its Orbiter Major Modification period, which began in December. Electrical modifications continue in the crew module. The Flash Evaporator System, which helps to cool the vehicle while in flight, was installed in the aft of the orbiter.

Three String Global Positioning System wire routing in the avionics bay and flight deck continues. The temporary installation of the nose cap is complete. The chin panel, which is the semicircle-shaped piece of Reinforced Carbon-Carbon insulation under the nose cap, is undergoing a fit-check.



- end -


text-only version of this release

To receive status reports and news releases issued from the Kennedy Space Center Newsroom electronically, send a blank e-mail message to ksc-subscribe@newsletters.nasa.gov. To unsubscribe, send a blank e-mail message to ksc-unsubscribe@newsletters.nasa.gov. The system will confirm your request via e-mail.

+ Back to Top
FirstGov - Your First Click to the US Government

ExpectMore.gov

+ Freedom of Information Act
+ Budgets, Strategic Plans and Accountability Reports
+ The President's Management Agenda
+ Privacy Policy and Important Notices
+ Inspector General Hotline
+ Equal Employment Opportunity Data Posted Pursuant to the No Fear Act
+ Information-Dissemination Priorities and Inventories
NASA
Editor: Linda Lynch
NASA Official: Brian Dunbar
Last Updated: January 5, 2007
+ Contact Kennedy
+ SiteMap