Follow this link to go to the text only version of nasa.gov
NASA -National Aeronautics and Space Administration
Follow this link to skip to the main content
+ Text Only Site
+ Site Help & Preferences
Go
ABOUT NASALATEST NEWSMULTIMEDIAMISSIONSMyNASAWORK FOR NASA

+ NASA Home
+ KSC Home
Kennedy Space Center
CENTER HOME
ABOUT KENNEDY
KENNEDY NEWS
KENNEDY MULTIMEDIA
MISSIONS
KENNEDY EVENTS
EDUCATION
DOING BUSINESS WITH US
SHUTTLE OPERATIONS
LAUNCHING ROCKETS
STATION PAYLOADS
Go
+ NASA Home > Centers > Kennedy Space Center > Shuttle Operations > Shuttle Status Reports > 2004
Print ThisPrint This
Email ThisEmail This

NASA NEWS

Allard Beutel
Headquarters, Washington
(Phone: 202/358-4769)

Jessica Rye
Kennedy Space Center, Fla.
(Phone: 321/867-2468)


April 15, 2004
RELEASE: S04-07

Space Shuttle Processing Status Report: S04-07

The Space Shuttle fleet is housed and processed at NASA's Kennedy Space Center (KSC), Fla. The order of the Space Shuttles in this report does not necessarily reflect the chronological order of future missions.

Discovery (OV-103)

Discovery is a step closer to its Return to Flight mission, STS-114, to the International Space Station. Vehicle power up work continues with communications system testing, drag chute instrumentation retest and wireless video system testing. The left-hand Orbital Maneuvering System pod is scheduled for installation Saturday. The launch planning window for STS-114 opens in March 2005.

Technicians successfully installed the four new Rudder Speed Brake actuators Wednesday. Panel installation is scheduled to begin early next week. Build-up of left-hand Reinforced Carbon-Carbon (RCC) panels and associated fittings is ongoing with 17 left-hand and six right-hand spar fittings installed on the vehicle.

Atlantis (OV-104)

Technicians continue to prepare Atlantis in the Orbiter Processing Facility for future flight to the International Space Station. Preparations for right and left Orbital Maneuvering System Main Engine removal are complete.

All of Atlantis' 44 RCC panels are at KSC, and all 22 panels have been hung on the left-hand wing. Nineteen left-hand T-seals, the C-shaped seals that fit between each panel, have been installed. Build-up of right-hand RCC panels and associated fittings is ongoing.

Endeavour (OV-105)

Space Shuttle Endeavour is in its Orbiter Major Modification (OMM) period, which began in December 2003. Electrical modifications associated with OMM continue in the crew module with the Multi-functional Electronic Display System, or the "glass cockpit."

The four Rudder Speed Brake actuators were removed from the vehicle and sent to the Titan X-ray Facility at Cape Canaveral Air Force Station to be X-rayed. The actuators will be sent to the vendor for a complete inspection.

Previous Space Shuttle processing status reports available on the Internet at:

http://www-pao.ksc.nasa.gov/kscpao/status/status.htm

For information about the NASA's Return to Flight efforts on the Internet, visit:

http://www.nasa.gov/returntoflight


For information about NASA and agency programs on the Internet, visit:

http://www.nasa.gov


- end -


text-only version of this release

To receive status reports and news releases issued from the Kennedy Space Center Newsroom electronically, send a blank e-mail message to ksc-subscribe@newsletters.nasa.gov. To unsubscribe, send a blank e-mail message to ksc-unsubscribe@newsletters.nasa.gov. The system will confirm your request via e-mail.

+ Back to Top
FirstGov - Your First Click to the US Government

ExpectMore.gov

+ Freedom of Information Act
+ Budgets, Strategic Plans and Accountability Reports
+ The President's Management Agenda
+ Privacy Policy and Important Notices
+ Inspector General Hotline
+ Equal Employment Opportunity Data Posted Pursuant to the No Fear Act
+ Information-Dissemination Priorities and Inventories
NASA
Editor: Jim Wilson
NASA Official: Brian Dunbar
Last Updated: January 5, 2007
+ Contact Kennedy
+ SiteMap