Follow this link to go to the text only version of nasa.gov
NASA -National Aeronautics and Space Administration
Follow this link to skip to the main content
+ Text Only Site
+ Site Help & Preferences
Go
ABOUT NASALATEST NEWSMULTIMEDIAMISSIONSMyNASAWORK FOR NASA

+ NASA Home
+ KSC Home
Kennedy Space Center
CENTER HOME
ABOUT KENNEDY
KENNEDY NEWS
KENNEDY MULTIMEDIA
MISSIONS
KENNEDY EVENTS
EDUCATION
DOING BUSINESS WITH US
SHUTTLE OPERATIONS
LAUNCHING ROCKETS
STATION PAYLOADS
Go
+ NASA Home > Centers > Kennedy Space Center > Shuttle Operations > Shuttle Status Reports > 2004
Print ThisPrint This
Email ThisEmail This

NASA NEWS

Allard Beutel
Headquarters, Washington
(Phone: 202/358-4769)

Jessica Rye
Kennedy Space Center, Florida
(Phone: 321/867-2468)


March 4, 2004
RELEASE: s04-001

Space Shuttle Processing Status Report: S04-01

The Space Shuttle fleet is housed and processed at NASA's Kennedy Space Center (KSC) in Florida. Every week, NASA will issue the latest information about Space Shuttle processing and payloads in a status report.

This Space Shuttle Processing Status Report is numbered S04-001. It corresponds with the Space Shuttle Processing Status Report Vol. 1 No. 2 issued from KSC. The content in both are identical. The order of the Space Shuttles in this report do not necessarily reflect the chronological order of future Space Shuttle missions. Previous reports are archived on the Internet at:

http://www-pao.ksc.nasa.gov/kscpao/status/status.htm

Discovery (OV-103)

Return to Flight preparations continue on orbiter Discovery in the processing facility at KSC. Following the decision by NASA management to remove and X-ray the Rudder Speed Brake actuator gears, the four actuators were removed from the vehicle and sent to the NASA Shuttle Logistics Depot in Cape Canaveral, Fla., for X-ray beginning Monday. The
X-ray will determine if the gears were installed correctly.

The Body Flap actuators are installed, with a fit check set for today. The Body Flap
re-installation is scheduled for Friday. Build-up of Reinforced Carbon-Carbon (RCC) panels and associated fittings is ongoing. The first RCC panels are scheduled to be hung starting early next week.

Atlantis (OV-104)

Processing of Atlantis continues at KSC in preparation for its future mission. Installation of the C-shaped T-seals that fit between each RCC panel is beginning on the left-hand wing leading edge. Right-hand RCC spar fittings are being installed, with the first panels being placed on the vehicle starting next week.

Remote Manipulator System hi-potential voltage tests are ongoing. Installation of window No. 2 is scheduled for next week.

Endeavour (OV-105)

Space Shuttle Endeavour is in its Orbiter Major Modification period, which began in December 2003. Thermal Protection System blankets are being removed to support removal and inspection of the Rudder Speed Brake actuators. RCC panels continue to be removed from the vehicle and returned to the vendor for inspection.

For more information about the NASA's Return to Flight efforts on the Internet, visit:

http://www.nasa.gov/news/highlights/returntoflight.html



- end -


text-only version of this release

To receive status reports and news releases issued from the Kennedy Space Center Newsroom electronically, send a blank e-mail message to ksc-subscribe@newsletters.nasa.gov. To unsubscribe, send a blank e-mail message to ksc-unsubscribe@newsletters.nasa.gov. The system will confirm your request via e-mail.

+ Back to Top
FirstGov - Your First Click to the US Government

ExpectMore.gov

+ Freedom of Information Act
+ Budgets, Strategic Plans and Accountability Reports
+ The President's Management Agenda
+ Privacy Policy and Important Notices
+ Inspector General Hotline
+ Equal Employment Opportunity Data Posted Pursuant to the No Fear Act
+ Information-Dissemination Priorities and Inventories
NASA
Editor: Jim Wilson
NASA Official: Brian Dunbar
Last Updated: January 5, 2007
+ Contact Kennedy
+ SiteMap