STATUS REPORT : S-19991208
 
 
KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
 
 
4:00 PM EST

MISSION: STS-103 -- 3rd HUBBLE SPACE TELESCOPE SERVICING MISSION

VEHICLE: Discovery/OV-103
LOCATION: Pad 39B
TARGET KSC LAUNCH DATE/TIME: December 11 at 11:42 p.m. EST (under review)
TARGET KSC LANDING DATE/TIME: December 21 at about 8:50 p.m. EST
LAUNCH WINDOW: 42 minutes
MISSION DURATION: about 9 days and 21 hours
CREW: Brown, Kelly, Smith, Foale, Grunsfeld, Nicollier, Clervoy
ORBITAL ALTITUDE and INCLINATION: 317 nautical miles/28.45 degrees
Work in progress: Shuttle managers have decided to delay the start of the STS-103 launch countdown by at least 24 hours while engineers evaluate a dented main propulsion system hydrogen line found during closeout inspections of Discovery's engine compartment. A final decision on whether or not the line must be replaced is expected tomorrow. If the line requires replacement, it is anticipated that the work would postpone launch by a minimum of several days. The four-inch diameter line carries liquid hydrogen fuel for the Space Shuttle main engines.

 

- end -


text-only version of this release

To receive status reports and news releases issued from the Kennedy Space Center Newsroom electronically, send a blank e-mail message to ksc-subscribe@newsletters.nasa.gov. To unsubscribe, send a blank e-mail message to ksc-unsubscribe@newsletters.nasa.gov. The system will confirm your request via e-mail.