STATUS REPORT : S-19991105
 
 
KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
 
 
4:00 PM EST

MISSION: STS-103 -- 3rd HUBBLE SPACE TELESCOPE SERVICING MISSION (HST-3)

VEHICLE: Discovery/OV-103
LOCATION: VAB
TARGET KSC LAUNCH DATE/TIME: early December (under review)
TARGET KSC LANDING DATE/TIME: mid-December (under review)
LAUNCH WINDOW: 42 minutes
MISSION DURATION: 10 days
CREW: Brown, Kelly, Smith, Foale, Grunsfeld, Nicollier, Clervoy
ORBITAL ALTITUDE and INCLINATION: 317 nautical miles/28.45 degrees
Work in progress: Orbiter Discovery has been mated to the external tank and solid rocket boosters stack in VAB high bay 1. Electrical and mechanical connections will conclude late Friday and the orbiter/external tank umbilical mate occurs Saturday. Over the weekend, workers will begin preparations for the engine No. 3 replacement work scheduled to happen at the launch pad. Managers currently plan to transfer Discovery out to Launch Pad 39B Tuesday, Nov. 9 beginning at about 2 a.m.

Payload managers plan to transfer the Hubble Servicing Mission cargo to the launch pad Monday, Nov. 8 with installation into the orbiter slated for Nov. 12.

KSC managers are developing the remainder of Discovery's prelaunch processing schedule and expect to brief Shuttle program managers at a meeting Monday morning. Program managers are likely to set a new target launch date for STS-103 after the meeting.

 

- end -


text-only version of this release

To receive status reports and news releases issued from the Kennedy Space Center Newsroom electronically, send a blank e-mail message to ksc-subscribe@newsletters.nasa.gov. To unsubscribe, send a blank e-mail message to ksc-unsubscribe@newsletters.nasa.gov. The system will confirm your request via e-mail.