NASA News

Kennedy Space Center, Fla.
321-867-2468


Nov. 29, 1995
 
STATUS REPORT : S-19951129
 
 
KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
 
 
2:12 PM EST

MISSION: STS-72 -- SFU-Retrieval & OAST-Flyer

VEHICLE: Endeavour/OV-105
LOCATION: Orbiter Processing Facility Bay 3
TARGET LAUNCH DATE/TIME: Jan. 11 at 4:18 a.m. EST
LAUNCH WINDOW: 60 minutes
TARGET KSC LANDING DATE/TIME: Jan. 20 at 2:54 a.m.
MISSION DURATION: 8 days, 22 hours, 36 minutes
CREW SIZE: 6
ORBITAL ALTITUDE and INCLINATION: 288 statute miles/28.45 degrees

NOTE: Endeavour’s rollover to the Vehicle Assembly Building has been delayed 24-hours due to problems encountered while lowering the orbiter onto the transporter and to allow extra time to finalize tests on the landing gear and associated electrical wiring. Move to the VAB is now set for no earlier than 8 a.m. tomorrow but more likely to occur around 12 noon. In the VAB, the orbiter will be mated to the external tank and solid rocket boosters. Rollout to pad 39B remains on schedule for Tuesday, Dec. 5.

KEY STS-72 OPERATIONAL MILESTONES (dates are target only):
* Roll to Vehicle Assembly Building (about 12 noon Thursday)
* Rollout to pad 39B (Dec. 5)
* Main engine flight readiness tests (Dec. 6-7)
* Terminal Countdown Demonstration Test ( Dec. 11-12)

MISSION: STS-75 -- TETHERED SATELLITE-1R & USMP-3

VEHICLE: Columbia/OV-102
LOCATION: Orbiter Processing Facility bay 2
TARGET LAUNCH DATE: Feb. 22
LAUNCH WINDOW: 2 hours, 30 minutes
TARGET KSC LANDING DATE: March 7
MISSION DURATION: 13 days, 16 hours
CREW SIZE: 7
ORBITAL ALTITUDE and INCLINATION: 184 statute miles/28.45 degrees

NOTE: Work today includes servicing the Freon coolant loops on Columbia. The forward reaction control system has been removed from the orbiter and preparations are in work to transport it to the Hypergolic Maintenance Facility for post-flight assessments and to replace a faulty thruster.

KEY STS-75 OPERATIONAL MILESTONES (dates are target only):
* Install main engines (Dec. 12)
* Install forward reaction control system (Dec. 19)

MISSION: STS-76 -- 3rd MIR DOCKING

VEHICLE: Atlantis/OV-104
LOCATION: Orbiter Processing Facility bay 1
TARGET LAUNCH DATE: March 21
LAUNCH WINDOW: about 6 minutes
TARGET KSC LANDING DATE: March 30
MISSION DURATION: 10 days (+1)
CREW SIZE: 6 up -- 5 down
ORBITAL ALTITUDE and INCLINATION: 196-245 statute miles/51.6 degrees

NOTE: Operations in work today include functional tests of the forward reaction control system and removal of the IMAX camera. The orbiter docking system will be removed later this week.

KEY STS-76 OPERATIONAL MILESTONES (dates are target only):
* Remove orbiter docking system (Dec. 2)
* Remove main engines (Dec. 12)
* Remove remote manipulator system (Dec. 12)
All times eastern

 

- end -


text-only version of this release

To receive status reports and news releases issued from the Kennedy Space Center Newsroom electronically, send a blank e-mail message to ksc-subscribe@newsletters.nasa.gov. To unsubscribe, send a blank e-mail message to ksc-unsubscribe@newsletters.nasa.gov. The system will confirm your request via e-mail.