STATUS REPORT : S-199509282
 
 
NASA's Space Shuttle Processing Status Report
 
 
Kennedy Space Center
Sept. 28, 1995 8:45 a.m.

STS-73 Columbia/USML 2 Launch Scrub

The launch of Space Shuttle Columbia was scrubbed at 4 a.m. today. During fueling operations a hydrogen leak was detected in main engine No. 1. It will be necessary to remove and replace the engine’s fuel valve, an operation which can be performed at the launch pad. The changeout work will be done this weekend. Also, the time-critical science experiments will be exchanged.

The countdown is tentatively planned to begin again on Monday, Oct. 2 and the launch targeted for Thursday, October 5 at 9:40 a.m.

 

- end -


text-only version of this release

To receive status reports and news releases issued from the Kennedy Space Center Newsroom electronically, send a blank e-mail message to ksc-subscribe@newsletters.nasa.gov. To unsubscribe, send a blank e-mail message to ksc-unsubscribe@newsletters.nasa.gov. The system will confirm your request via e-mail.