STATUS REPORT : S-19950920
 
 
NASA's Space Shuttle Processing Status Report
 
 
MISSION: STS-73 -- U.S. MICROGRAVITY LABORATORY-2

VEHICLE: Columbia/OV-102
LOCATION: Pad 39B
TARGET LAUNCH DATE/TIME: Sept. 28 at 9:35 a.m. EDT
LAUNCH WINDOW: 2 hours, 30 minutes
TARGET KSC LANDING DATE/TIME: Oct. 14 at 7:30 a.m.
MISSION DURATION: 15 days, 21 hours, 55 minutes
CREW SIZE: 7
ORBITAL ALTITUDE and INCLINATION: 172 statute miles/39 degrees

IN WORK TODAY:
* Aft engine compartment close-outs
* Continue ordnance operations
* Hypergolic fuel pressurization

WORK COMPLETED:
* Prelaunch propellant load
* Auxiliary power unit hot fire

KEY OPERATIONAL MILESTONES (dates are target only):
* Functional check-out of contingency spacesuits (Thursday)
* Begin countdown (4 a.m. Monday)
* STS-73 crew arrival at KSC (7 a.m. Monday)

MISSION: STS-74 -- 2nd MIR DOCKING (Docking Module)

VEHICLE: Atlantis/OV-104
LOCATION: Orbiter Processing Facility bay 2
TARGET LAUNCH DATE/TIME: Nov. 2 at 11:25 a.m. EST
LAUNCH WINDOW: 9 minutes, 14 seconds
TARGET MIR DOCKING DATE: Nov. 5
TARGET KSC LANDING DATE/TIME: Nov. 10 at 8:30 a.m.
MISSION DURATION: 7 days, 21 hours
CREW SIZE: 5
ORBITAL ALTITUDE and INCLINATION: 196-245 statute miles/51.6 degrees

KEY OPERATIONAL MILESTONES (dates are target only):
* Docking module interface verification test (Wednesday/Thursday)
* Final payload bay door closure (Sept. 26)
* Roll to Vehicle Assembly Building (Oct. 2)
* Move to Pad 39A (Oct. 9)

MISSION: STS-72 -- SFU-Retrieval & OAST-Flyer

VEHICLE: Endeavour/OV-105
LOCATION: Orbiter Processing Facility bay 3
TARGET LAUNCH DATE/TIME: Jan. 11 at 5:04 a.m. EST
LAUNCH WINDOW: 38 minutes
TARGET KSC LANDING DATE/TIME: Jan. 20 at 3:14 a.m.
MISSION DURATION: 8 days, 22 hours, 11 minutes
CREW SIZE: 6
ORBITAL ALTITUDE and INCLINATION: 184 statute miles/28.45 degrees

NOTE: Post-mission servicing of Endeavour following Monday’s landing at KSC continues in OPF bay 3. Jack and leveling operations are complete and work has begun to drain the residual cryogenic reactants from the orbiter’s onboard fuel cell supply tanks. The payload bay doors will be open tomorrow and the payloads removed on Saturday.

DISCOVERY/OV-103 -- Pre-Orbiter Maintenance Down Period

VEHICLE: Discovery/OV-103
LOCATION: Orbiter Processing Facility bay 1
DATE OF DEPARTURE FOR PALMDALE, CALIF.: Sept. 26

NOTE: Discovery is scheduled to be delivered to Palmdale, Calif., for a nine-month Orbiter Maintenance Down Period (OMDP). During this time, the vehicle will be outfitted with a 5th set of cryogenic tanks and an external airlock to support missions to the international Space Station. Discovery is scheduled to depart KSC via the 747 Shuttle Carrier Aircraft (SCA) on Tuesday, Sept. 26. Discovery’s next flight, the second mission to service the Hubble Space Telescope, is targeted for launch in early 1997.

KEY OPERATIONAL MILESTONES:
* Install protective tail cone (in work today)
* Place orbiter on transporter and retract landing (Friday)
* Move orbiter to Shuttle Landing Facility for mate with 747 SCA (Monday)

 

- end -


text-only version of this release

To receive status reports and news releases issued from the Kennedy Space Center Newsroom electronically, send a blank e-mail message to ksc-subscribe@newsletters.nasa.gov. To unsubscribe, send a blank e-mail message to ksc-unsubscribe@newsletters.nasa.gov. The system will confirm your request via e-mail.