NASA News

Kennedy Space Center, Fla.
321-867-2468


Aug. 18, 1995
 
STATUS REPORT : S-19950818
 
 
NASA's Space Shuttle Processing Status Report
 
 
Vehicle: OV-105/Endeavour
Mission number: STS-69
Location: Pad 39-A
Primary payload: Wake Shield Facility/Spartan 201-3
Astronauts: 5
Orbital altitude: 230 statute miles
Inclination: 28.45 degrees
Mission Duration: 10 days, 20 hours, 29 minutes
Launch date: late August
Landing date: TBD

STS-69 IN WORK:

· Solid rocket booster nozzle plug removal

STS-69 WORK SCHEDULED:

· Begin solid rocket booster RTV excavation (Saturday)

STS-69 WORK COMPLETED:

· Completion and sign-off of solid rocket booster repair procedure

Columbia/OV-102 (STS-73) U.S. Microgravity Laboratory
OPF Bay 3

The startracker door is being reinstalled today and the orbiter is being jacked down in preparation for the weight and center of gravity determination which is scheduled for tonight. Tile waterproofing and installation of Columbia onto the orbiter transporter will occur this weekend. Rollover of Columbia to the VAB is scheduled for Monday, August 21 at 9 a.m. Rollout to Pad 39-B is scheduled for Aug. 28. The Terminal Countdown Demonstration Test is tentatively planned for a T-0 at 11 a.m. on Sept. 1.

Atlantis/OV-104 (STS-74) Russian Docking Module
OPF Bay 2

Ammonia boiler servicing was performed last night. Mid-body closeouts are continuing. The functional test of the orbital maneuvering system have been completed. Reaction control system testing is scheduled to begin next week. Preparations are beginning for the installation of the tunnel adapter.

In the Vehicle Assembly Building, mechanical testing of the orbiter docking system is being performed today. Stacking of the left forward center solid rocket booster segment is complete. Preparations to hoist the right booster aft segment onto the mobile launcher platform will begin tonight with the arrival of the segment in the VAB.

In the Operations and Checkout Building, the Russian MIR-2 Docking Module is being hoisted from the payload canister into a test stand to begin approximately three weeks of electrical testing.

Discovery/OV-103
OPF Bay 1

Work continues to deconfigure and deservice Discovery in preparation for the ferry flight to Palmdale which is planned to begin on or about Oct. 1.

KSC 24-Hour Weather Summary
Shuttle Landing Facility
Today’s minimum temperature: 78 degrees
Yesterday’s maximum temperature: 93 degrees
Lowest relative humidity: 49 percent
Peak wind speed/direction: 16 mph/ESE
Precipitation as of 7 a.m.: 0
Total monthly precipitation: 2.55 inches
Barometric pressure at 7 a.m.: 29.92 inches

 

- end -


text-only version of this release

To receive status reports and news releases issued from the Kennedy Space Center Newsroom electronically, send a blank e-mail message to ksc-subscribe@newsletters.nasa.gov. To unsubscribe, send a blank e-mail message to ksc-unsubscribe@newsletters.nasa.gov. The system will confirm your request via e-mail.