NASA News

Kennedy Space Center, Fla.
321-867-2468


April 19, 1995
 
STATUS REPORT : S-19950419
 
 
NASA's Space Shuttle Processing Status Report
 
 
NOTE: Missions STS-71 and STS-70 are both being targeted for no earlier than launch dates. Options are being protected for each to be the next one launched.

MISSION: STS-71 -- 1st MIR DOCKING

VEHICLE: Atlantis/OV-104
LOCATION: Orbiter Processing Facility bay 3
*TARGET LAUNCH DATE: June 19 (no earlier than)
*APPROX. LAUNCH TIME: 6:43 p.m. EDT
LAUNCH WINDOW: 5 minutes
*KSC LANDING DATE/TIME: June 30 at 2:14 p.m.
MISSION DURATION: 10 days, 19 hours, 31 minutes
CREW SIZE: 7 up, 8 down
ORBITAL ALTITUDE and INCLINATION: 196-245 statute miles/51.60 degrees
* change from earlier status

IN WORK TODAY:
Preparations for move to Vehicle Assembly Building
Crew hatch and forward compartment close-outs
Weight and center of gravity checks

WORK COMPLETED:
Final Orbiter Docking System checks
Close payload bay doors
Final payload bay cleaning and inspections

KEY OPERATIONAL MILESTONES (dates are target only):
Roll orbiter to Vehicle Assembly Building (12 p.m. (noon) Thursday)
Roll Shuttle vehicle to Launch Pad 39-A (April 26)
Hot fire auxiliary power units (April 27)
Terminal Countdown Demonstration Test (May 16-17)

MISSION: STS-70 -- TDRS-G

VEHICLE: Discovery/OV-103
LOCATION: Orbiter Processing Facility bay 2
TARGET LAUNCH DATE: June 8 (no earlier than)
APPROX. LAUNCH TIME: 10:20 a.m.
LAUNCH WINDOW: 2 hours, 30 minutes
TARGET KSC LANDING DATE/TIME: June 16 at 8:33 a.m.
MISSION DURATION: 7 days, 22 hours
CREW SIZE: 5
ORBITAL ALTITUDE and INCLINATION: 184 statute miles/28.45 degrees

IN WORK TODAY:
Secure space shuttle main engines
Orbital maneuvering system check-outs
Landing gear functional checks

WORK COMPLETED:
Install shuttle main engines

KEY OPERATIONAL MILESTONES (dates are target only):
Close payload bay doors (April 25)
Roll orbiter to Vehicle Assembly Building (May 3)
Roll Shuttle vehicle to Launch Pad 39-B (May 11)

MISSION: STS-69 -- WSF-2 & SPARTAN 201-03

VEHICLE: Endeavour/OV-105
LOCATION: Orbiter Processing Facility bay 1
TARGET LAUNCH DATE/TIME: July 20 at 12:06 p.m.
LAUNCH WINDOW: 2 hours, 30 minutes
TARGET KSC LANDING DATE/TIME: July 31 at 8:37 a.m.
MISSION DURATION: 10 days, 21 hours
CREW SIZE: 5
ORBITAL ALTITUDE and INCLINATION: 190 statute miles/28.45 degrees

NOTE: Endeavour is powered-up as work continues to perform functional checks on the left and right hand orbital maneuvering system pods. Also, the main landing gear wheel and tire assemblies are being readied for installation.

MISSION: STS-73 -- U.S. MICROGRAVITY LABORATORY-2

VEHICLE: Columbia/OV-102
LOCATION: Vehicle Assembly Building bay 2
TARGET LAUNCH DATE/TIME: Sept. 21 at 10:37 a.m.
LAUNCH WINDOW: 2 hours, 30 minutes
TARGET KSC LANDING DATE/TIME: Oct. 7 at 8:31 a.m.
MISSION DURATION: 16 days
CREW SIZE: 7
ORBITAL ALTITUDE and INCLINATION: 167 statute miles/39 degrees

NOTE: The orbiter Columbia remains in the Vehicle Assembly Building awaiting Atlantis’ departure from the Orbiter Processing Facility bay 3. Columbia will move into the OPF early Friday morning and preparations will begin for its next mission, STS-73.

 

- end -


text-only version of this release

To receive status reports and news releases issued from the Kennedy Space Center Newsroom electronically, send a blank e-mail message to ksc-subscribe@newsletters.nasa.gov. To unsubscribe, send a blank e-mail message to ksc-unsubscribe@newsletters.nasa.gov. The system will confirm your request via e-mail.