Dec. 9, 1994
 
STATUS REPORT : S-19941209
 
 
NASA's Space Shuttle Processing Status Report
 
 
MISSION: STS-63 -- MIR RENDEZVOUS, SPARTAN and SPACEHAB-3

VEHICLE: Discovery/OV-103
LOCATION: OPF bay 2
TARGET LAUNCH DATE/TIME: Feb. 2, 1995 at 12:51 a.m. EST
LAUNCH WINDOW: 5 minutes
TARGET KSC LANDING DATE/TIME: Feb. 10 at 7:05 a.m.
MISSION DURATION: 8 days, 6 hours, 13 minutes
CREW SIZE: 6
ORBITAL ALTITUDE: 196 statute miles
INCLINATION: 51.60 degrees

IN WORK TODAY:
Spartan electrical interface modification
Orbital maneuvering system pod interface verification test
Aft engine compartment close-outs and final engine checks
Auxiliary power unit no. 2 inspections and verifications

WORK COMPLETED:
Install main engine heatshields
Install left hand orbital maneuvering system pod
Potable water servicing
Main engine securing and inspections

WORK SCHEDULED NEXT WEEK:
Crew equipment interface test (Saturday)
Complete payload interface verification checks
Main engine clearance and final aerosurface checks
Orbital maneuvering system pod crossfeed connections
Orbiter mid-body close-outs
Close payload bay doors for flight

MISSION: STS-67 -- Astro-2

VEHICLE: Endeavour/OV-105
LOCATION: OPF bay 1
TARGET LAUNCH PERIOD: early March
APPROX. LAUNCH TIME: very early morning
LAUNCH WINDOW: 2 hours, 3 minutes
KSC LANDING DATE/TIME: TBD
MISSION DURATION: 15 days, 13 hours
CREW SIZE: 7
ORBITAL ALTITUDE: 218 statute miles
INCLINATION: 28.45 degrees

IN WORK TODAY:
Clear bay for work on disconnecting auxiliary power unit no. 1
Stack solid rocket boosters in Vehicle Assembly Building

WORK COMPLETED:
Extended duration orbiter pallet leak checks
Hydraulic flight control tests
Water spray boiler installation
Nose wheel steering checks
Payload bay close-outs
Functional checks of orbital maneuvering system pods

WORK SCHEDULED NEXT WEEK:
Continue payload premate tests
Install ASTRO-2 payload and interface verification checks
Continue main propulsion system verification checks
Begin aft engine compartment close-outs
Begin preparations to install main engines

MISSION: STS-71 -- 1st MIR DOCKING

VEHICLE: Atlantis/OV-104
LOCATION: OPF bay 3
TARGET LAUNCH PERIOD: late May
APPROX. LAUNCH TIME: early morning
LAUNCH WINDOW: 5 minutes
KSC LANDING DATE/TIME: TBD
MISSION DURATION: 9 days, 20 hours
CREW SIZE: 7 up, 8 down
ORBITAL ALTITUDE: 196-245 statute miles
INCLINATION: 51.60 degrees

IN WORK TODAY:
Orbiter structural checks
Main propulsion system verification checks
Main engine pump torque checks
Close payload bay doors

WORK COMPLETED:
Remove remote manipulator system
Fuel cell leak checks
Remove payloads

WORK SCHEDULED NEXT WEEK:
Off load hypergolic reactants
Open payload bay doors
Remove and replace orbital maneuvering system thrusters

 

- end -


text-only version of this release

To receive status reports and news releases issued from the Kennedy Space Center Newsroom electronically, send a blank e-mail message to ksc-subscribe@newsletters.nasa.gov. To unsubscribe, send a blank e-mail message to ksc-unsubscribe@newsletters.nasa.gov. The system will confirm your request via e-mail.