NASA News

Kennedy Space Center, Fla.
321-867-2468


Dec. 7, 1994
 
STATUS REPORT : S-19941207
 
 
NASA's Space Shuttle Processing Status Report
 
 
MISSION: STS-63

VEHICLE: Discovery/OV-103
ORBITAL ALTITUDE: 196 sm
LOCATION: OPF bay 2
INCLINATION: 51.60 degrees
TARGET LAUNCH DATE: Feb. 2, 1995
CREW SIZE: 6
LAUNCH TIME: 12:51 a.m. EST
LAUNCH WINDOW: 5 minutes
TARGET KSC LANDING DATE/TIME: Feb. 10/7:05 a.m.
MISSION DURATION: 8D/6H/13M

IN WORK TODAY:
Install left hand orbital maneuvering system pod
Payload interface verification test
Begin orbiter aft engine compartment closeouts
Potable water servicing

WORK COMPLETED:
Transport left hand orbital maneuvering system pod to OPF
Main engine securing and inspections
Install main engine heatshields

WORK SCHEDULED:
Orbital maneuvering system pod interface verification test
Crew equipment interface test

MISSION: STS-67 -- Astro-2

VEHICLE: Endeavour/OV-105
ORBITAL ALTITUDE: 218 sm
LOCATION: OPF bay 1
INCLINATION: 28.45 degrees
TARGET LAUNCH PERIOD: early March
CREW SIZE: 7
APPROX. LAUNCH TIME: very early morning
LAUNCH WINDOW: 2H/3M
KSC LANDING DATE/TIME: TBD
MISSION DURATION: 15D/13H

IN WORK TODAY:
Payload premate tests
Main propulsion system verification checks
Nose wheel steering checks
Hydraulic system fill and bleed
Stack solid rocket boosters in Vehicle Assembly Building

WORK SCHEDULED:
Install auxiliary power unit no. 1
Preparations to install main engines

WORK COMPLETED:
Water spray boiler installation
Electrical mates of the extended duration orbiter pallet
Payload bay closeouts
Functional checks of orbital maneuvering system pods

MISSION: STS-71 -- 1st MIR DOCKING

VEHICLE: Atlantis/OV-104
ORBITAL ALTITUDE: 196-245 sm
LOCATION: OPF bay 3
INCLINATION: 51.60 degrees
TARGET LAUNCH PERIOD: late May
CREW SIZE: 7/8
APPROX. LAUNCH TIME: early morning
LAUNCH WINDOW: 5 minutes
KSC LANDING DATE/TIME: TBD
MISSION DURATION: 9D/20H

IN WORK TODAY:
Orbiter structural checks
Fuel cell checks

WORK COMPLETED:
Remove payloads
Forward reaction control system functional test
Initial inspections of orbiter docking system
Open payload bay doors

WORK SCHEDULED:
Cycle payload bay doors

 

- end -


text-only version of this release

To receive status reports and news releases issued from the Kennedy Space Center Newsroom electronically, send a blank e-mail message to ksc-subscribe@newsletters.nasa.gov. To unsubscribe, send a blank e-mail message to ksc-unsubscribe@newsletters.nasa.gov. The system will confirm your request via e-mail.