  • Expendable Launch Vehicle Status Report

    09.14.07 - On Tuesday, the Dawn spacecraft arrived at Pad 17-B at 5:10 a.m. after an overnight rollout from the Astrotech payload processing facility and was secured atop the Delta II rocket.

  • Expendable Launch Vehicle Status Report

    09.07.07 - Dawn spacecraft operational readiness testing is complete. Technicians will be installing Dawn into the payload canister on Sept. 10 for transportation to Launch Complex 17.

  • Expendable Launch Vehicle Status Report

    07.27.07 - Phoenix was transported to Pad 17-A at Cape Canaveral Air Force Station for mating to the Delta II on Monday, July 23. The flight program verification test was successful.

  • Expendable Launch Vehicle Status Report

    07.20.07 - Mating of Phoenix to the upper-stage booster occurred Tuesday, July 17. Spacecraft engineers installed the heat shield onto the cruise stage Thursday, July 19.

  • Expendable Launch Vehicle Status Report

    07.13.07 - Engineers successfully performed the spin testing of Phoenix this week. Mating of Phoenix to the upper-stage booster is scheduled for July 17.

  • Expendable Launch Vehicle Status Report

    07.03.07 - The flight readiness review for NASA's Dawn spacecraft was completed on Tuesday. All technical issues were cleared.

  • Expendable Launch Vehicle Status Report

    06.27.07 - NASA's Dawn spacecraft is on the pad and being prepared for Flight Program Verification on June 29.

  • Expendable Launch Vehicle Status Report

    06.18.07 - Over the weekend, Dutch Space personnel completed the solar array repair on NASA's Dawn spacecraft as planned, and spacecraft processing continues on schedule.

  • Expendable Launch Vehicle Status Report

    06.14.07 - NASA is investigating a minor mishap affecting the Dawn spacecraft. During a procedure to prepare the spacecraft for testing, the back of a solar array panel was slightly damaged.

  • Expendable Launch Vehicle Status Report

    06.06.07 - The Delta II first stage for the Dawn mission was hoisted into the launcher after a postponement due to high wind at the launch pad. Erection of the nine solid rocket boosters then began.

  • Expendable Launch Vehicle Status Report

    05.25.07 - Solar array installation and deployment tests on Dawn are scheduled to be completed Friday. It is scheduled to move to the hazardous processing facility on May 28.

  • Expendable Launch Vehicle Status Report

    05.18.07 - Next week, the two spacecraft solar arrays, each consisting of four panels, will be attached to the Dawn spacecraft and undergo deployment testing.

  • Expendable Launch Vehicle Status Report

    05.11.07 - Mission system performance testing continues on NASA's Dawn spacecraft and is planned to finish Friday. Processing of NASA's Phoenix spacecraft is also under way.

  • Expendable Launch Vehicle Status Report

    05.07.07 - Comprehensive performance testing continues on NASA's Dawn spacecraft. A test of the primary communications antenna is scheduled for May 21.

  • Expendable Launch Vehicle Status Report

    04.27.07 - The "command and data handling" portion of the Comprehensive Performance Test was completed on April 19 on the Dawn spacecraft. Additional tests are in progress.

  • Expendable Launch Vehicle Status Report

    04.23.07 - NASA's AIM spacecraft was mated to the Pegasus XL rocket on April 4, and an integrated flight simulation was successfully completed during the week of April 13.

  • Expendable Launch Vehicle Status Report

    04.13.07 - NASA's AIM spacecraft was mated to the Pegasus XL rocket on April 4. An integrated flight simulation was successfully completed earlier this week.

  • Expendable Launch Vehicle Status Report

    04.06.07 - NASA's Aeronomy of Ice in the Mesosphere (AIM) spacecraft was mated to the Pegasus XL rocket on Wednesday. An integrated flight simulation is scheduled for early next week.

  • Expendable Launch Vehicle Status Report

    03.30.07 - Technicians have completed cleaning and calibrating the instruments and installed the spacecraft separation system on NASA's Aeronomy of Ice in the Mesosphere (AIM) spacecraft.

  • Expendable Launch Vehicle Status Report

    03.23.07 - Since NASA's Aeronomy of Ice in the Mesosphere (AIM) spacecraft arrived at Vandenberg Air Force Base on March 10, the prelaunch processing has gone well and is on schedule.

  • Expendable Launch Vehicle Status Report

    02.13.07 - The launch of THEMIS (Time History of Events and Macroscale Interactions During Substorms) aboard a Delta II rocket scheduled for Thursday, Feb. 15, has been postponed 24 hours.

  • Expendable Launch Vehicle Status Report

    02.09.07 - THEMIS was transported from Astrotech payload processing facility to Pad 17-B. The final major test, the Flight Program Verification, was successfully conducted on Feb. 6.

  • Expendable Launch Vehicle Status Report

    02.02.07 - At the Astrotech payload processing facility near Kennedy Space Center, transportation of THEMIS to Pad 17-B was rescheduled from today until early Saturday morning.

  • Expendable Launch Vehicle Status Report

    01.26.07 - At the Astrotech payload processing facility near KSC, engineers and technicians are preparing the THEMIS spacecraft for mating to the upper stage booster, planned for Monday.

  • Expendable Launch Vehicle Status Report

    01.19.07 - At the Astrotech payload processing facility near Kennedy Space Center, engineers and technicians successfully completed spin-balance testing of THEMIS on Jan. 12.

  • Expendable Launch Vehicle Status Report

    01.12.07 - At the Astrotech payload processing facility near Kennedy Space Center, engineers finished installing the five THEMIS probes onto the spacecraft's probe carrier on Wednesday.

  • Expendable Launch Vehicle Status Report

    01.05.07 - At the Astrotech payload processing facility, fueling of the THEMIS spacecraft is under way this week. The probes will be installed onto the payload carrier Jan. 9 to 11.